Sunday, March 29, 2009

Latest Update 30/03/09





To all 1sentulians,  

Progress of the day :

-Construction of "rumah kongsi" started yesterday.Almost 50 % completed.They will "full swing/pulun habis" after  "rumah kongsi (as accomodation for workers) completed by end of this week.

-Perimeter drainage system also just started today.

cheers.

zoul3d

 

Thursday, March 26, 2009

Breaking news!!! 3rd week.Latest Update 27/03/09




Breaking news!!!latest progress on site.Site look so busy today. Welcome brian!!

1st week- After a great news from Casper



Our site - first week. A small excavator clearing the site.

Zalam Corp. , as a main contractor of 1sentul.Thanks to brian for this photo.

Introduction





Hi guys,,this blog specially created for all 1sentulians.I 'll try to update the progress of our property.We also can discuss anythings about 1sentul here.

cheers,

zoul3d